Holiday World & Splashin' Safari Santa Claus, Indiana
2006 Construction Update
April 1, 2006
With The Voyage it seems like
most of the work is on the little final touches as all of the structure
is in place and they've got to be pretty close to completing the track.
About the most visible work on The Voyage from the highway is the continued
work on the tunnel for the triple-down. The roof is in place while
the walls are yet to be completed.
The most visible work that's
going on for Holiday World's huge 60th season expansion is over at Gobbler
Getaway where in a week we've gone from studded walls to having the
siding being put on.
I'm not sure when the guts of Gobbler
Getaway is going to start appearing but earlier this week several of
the animatronic figures for it could be seen on the Sally Dark Rides
webcam.
Another finishing touch this week
has been with the completion of the bridge down into Thanksgiving.
There has been a lot of work up hill from here so chances are they're
getting the new path down into Thanksgiving together.
Well there's just 33 days to go
until opening day so they're extremely busy over at Holiday World.
To all of those over there working hard to get the park ready for opening
day thank you.